The employer must provide drawings together with a description of works, and either a specification or work schedules at tender stage. The project is generally not complex enough to require bills of quantities.
The price and payment structure of the contract is based on a lump sum with monthly interim payments.
Sub-Contractors can be appointed with written permission of the architect/contract administrator or selected from a list of three names.
Provisions are included for collaborative working, sustainability, advance payment, bonds (advance payment, off-site materials, retention), third party rights and collateral warranties, named specialists, and a 'Contractor's Designed Portion'.
Pre-Construction Services Agreement (General Contractor) (PCSA) and Pre-Construction Services Agreement (Specialist) (PCSA/SP) can be used with this contract.
This contract can be used with the Framework Agreement (FA).
For use of both private and public sector projects.